Timeline
POSSIBLE TIME LINE:
- Report given to AEA and APS boards with recommendation to proceed - September 4, 2007
- APS board reviews report - September 4, 2007
- AEA board reviews report - September 4, 2007
- Present report to AR Council - September 11, 2007
- Share general concept with all schools - September 14 - October 1, 2007
- Potential contract language developed through negotiations - October 3 and 10, 2007
- AEA approves contract language - October 15-19, 2007
- BOE approves Pilot School program - October 23, 2007
- Begin forming Joint Steering Committee - Early October, 2007
- Continue communication to schools/community - October/November 2007
- Hold two info forums for interested schools - November 2007
- Call for Request for Proposals for 2008-09 - November 1, 2007
- Letter of intent due - November 20, 2007
- Design team training - November 26-30, 2007
- Submission of proposals to Joint Steering Committee - January 15, 2008
- Joint steering makes recommendations to BOE - February 13, 2008
- BOE announces selections - February 19, 2008
- First school(s) open - August 2008
- GOAL: MINIMUM OF THREE SCHOOLS BY 2010 - Accomplished